Pool Cover On

The pool cover has been placed over the pool shell. This is done whilst the rest of the house is built. Effectively the cover is a work platform and can hold up to 225kg.

We found out during the pool excavation that our Pool supervisor had left Rogers Pools and we have a new one and then on Friday we found that we were being handed over to a new supervisor at Stylemaster as well. Not really a big deal with Stylemaster at this stage because we haven’t really started and I hadn’t met the original one so as long as that is it then that is OK.

Now it is back over to Sytlemaster to get into the house build proper. The next step is to prepare the house piering, under slab plumbing and then the slab can go down. That will be at least a few weeks away before that starts, especially as next week is Easter so there won’t be much action for a while unfortunately.